The 8 Essential Review Questions
Ensure every field decision documented in Procore covers these critical components.
Original Condition
Document what the contract drawings originally specified versus the actual physical conditions encountered on site. Detail the discrepancy precisely.
Project Requirement
Identify the governing specification section, architectural detail sheet, local building code, or engineering standard that controls the design.
Affected Trades
List all subcontractors and trades impacted by the change in layout, sequence, or structural access. Coordinate interface points to prevent field conflicts.
Decision Owner
Clarify who owns the final technical and financial sign-off. Clearly map whether the architect, structural engineer, owner rep, or lead superintendent must issue the directive.
Unresolved Question
Formulate the exact question that needs answering. Avoid vague requests for advice; write structured, clear options (e.g., Option A vs Option B) to expedite approval.
Schedule Impact
State whether this decision affects the critical path. Estimate days of delay or potential acceleration to keep schedule logs up to date.
Final Resolution
Write down the concrete directive or solution provided by the design team. Avoid logging hearsay—only log written responses from authorized agents.
Handoff Context
Translate the technical RFI resolution into plain language instructions for site superintendents, foremen, and safety managers executing the work.